Minutes
of Technology Advisory Board Meeting
of August 15, 2006
Present: J Tasse, Chairman, G. Eggleston, J.
Kelley, M. Schorr, P. St. John, B. Gardner-Town Board liaison
The meeting was called to order at 7:09 pm.
1. The minutes of the 7-18-06 meeting were
approved with one change.
2. Tasse
handed out copies of quotes received by the Town Clerk for a computer for her
grant on records retention. The quotes from Dell, Tech Depot (for an Hp), Hp
(for an Hp at govt. price), all laptops with Intel dual-core processors, were
reviewed. The Dell was the lowest
price, but did not have a docking station which the others had. The Dell quote
has 2-years service while the Hp units have one year. The TAB recommends that Heather
go back to Dell for a quote for a unit with a docking station so that the
quotes can be compared on an equal basis. If the Hp is selected, it should
probably be the lower priced one.
3. Town
Hall Computer Survey Forms – George provided a summary table of the forms
received to date. Forms have not yet been received from the assessors (V.
Hayner said she will provide it), the justices and the Town Clerk. There are at
least 5 additional computers in use that were not covered by the forms
received. Discussion – personal-owned home computers should not be used for
Town business; It is recommended that all Town employees using computers for
Town business have a Town owned computer. Conclusion – there should be standard
procedures and needs for computer security. If easily transferable to the new
Town Hall, a server should be purchased now and at least a start made in
getting more PCs and uniform virus protection for all Town owned computers.
Based on discussion of server capabilities, at least $5,000 should be allocated
in the budget for a server (see attachment for server spec). The outage of the
Town Clerks computer should serve as a warning of the need for a server. ACTION
- Kelley will outline the general security procedures for the operating system
(see also his 4/18/06 write-up, Town of Charlton Network Setup Options for the
New Town Hall).
4. Employee
Manual–Comments on Section 511, Computer Systems and Internet/E-mail Service,
were discussed and given to Bruce Gardner.
The Town of Charlton Computer Security and System Functional Requirements
drafted by J. Tasse and provided at the last meeting were also discussed and
comments provided to Bruce.
5. The
need for possible new accounting system software was discussed.
The meeting was adjourned at 9:20 pm.
Prepared
by M. Schorr
Town of Charlton Technology Advisory Board
8/16/06
Specification of Town server minimum requirements
q
Processer – Pentium core duo 2.5 GHz +
q
Storage space – 500 GB
q
Expandability – 4 extra disk bays
q
Drive protocol – SATA
q
Raid capability – system should support RAID 5
q
Operating System – Windows Small business Server 2003
q
PCI slots – minimum of 2
q
Network ports – 2 minimum
q
System must support use of McAffee managed virus scan
q
Other items
o
Minimum of 2 USB ports
o
Extra fan installed or shipped separate
Other server installation considerations
q
Current town hall requires rewiring
q
USB tape backup
q
“Smart” uninterruptable power supply
q
Consultant services for installation, setup,
configuration, and training of Town designated superuser